17 August 2016
Update on 11 Hallikeld Close
Slow, very slow progress, since my June update. Basically, it's just been a staircase that meets building regulations and finishing off the mezzanine floor.
But the white food-grade walls were delivered today from Hemsec Panel Technologies, so the new tea-packing room should constructed by Friday. All we'll then be waiting for is to complete the rooms is a gully drain to be cut out and connected, then a blue resin floor can be laid and plumbing fitted.
The tea packing machine is due for early September. I am not sure it will get through the doors into the building, but everyone is telling me it'll be fine - let's see what happens then, shall we.